UNILOFTS STUDENT ACCOMMODATION
Monday, August 15, 2011
Second Phase Basement nears completion.
Tuesday, August 2, 2011
Block F and Block E on level and the roof is being installed.
Wednesday, July 20, 2011
The Roof of Block F nears completion.
Friday, July 1, 2011
The Structure is 61% Complete. Second Phase well on its way.
Tuesday, June 28, 2011
An average of 12,000 bricks per day. UNILOFTS well on target.
Monday, June 20, 2011
The Progress of block F and block E in 14 days - Well done Archstone !!
Friday, June 3, 2011
The Second Phase columns are been prepared for casting